FAQ: Plant Maintenance Cut-Over Activities/Tasks

$
0
0

Here is a list of cut-over tasks that should be considered during go-live.


Please contribute:

 

  • Create default variants for selection screens e.g. IW28/9
  • Create default layouts for ALV displays e.g. IW38/9
  • Strategies for maintenance plans
  • Create initial measurement documents which are required for counter based maintenance plans
  • Schedule maintenance plans from start-date of go-live
  • Number ranges (manual transports)
  • Data for application Z tables (i.e. non-customizing tables)
  • QuickView/ABAP Query reports
  • Transfer open orders/notifications from legacy system to SAP
  • Classes & Characteristics (you can ALE these from one system to another)
  • Batch programs/interfaces: e.g. schedule background jobs like IP30/CO99/KO8G, custom developed reports/programs, etc.
  • Run program RI_IFLOT2IFLOS if you are using alternative labels for functional locations
  • Stock levels for maintenance spares
  • SmartForm fonts
  • Printer settings for barcodes
  • Parameter ID settings (transaction SU3)
  • User favorite menus (requires Z program)
  • User personal lists (requires Z program)
  • Selection-variable settings (transaction STVARV )